2022-11-26
Pump house construction
Brick and MSand reached site today. Gave adv for saaram to mason. Asked venkatesan to bring along cement 7 bags.
Vamban8 and gingelley
6kg per acre, 2 pack rhizobium per acre. Monday is auspicious. Suggested gingelley 2 bag complex spic, if no then fact elephant, if not vijay per acre Gingelley 2kg + 10kg sand for entire 11 acre
Pump house estimate
Finished
Bricks sakthi aruvapakkam 21/31 6"/8"*16" ₹8200 MSand 3100 Transport 2000+labour1800+food ₹700 Adv ₹1500 Labor ₹200 Total as on date: ₹17,500
Pending Cement sheet 2*1, 3*1 395/595 Sq pipe 1*1 1.6mm/ 2mm ,7kg/9kg 81 585 per length Rect pipe 1.5*0.75 1.6mm ,9kg +1+1
Estimates Kalai Sheet 5*630 ₹3150 Cement sheet ₹4000 GI pipe 1" 5*6*₹150 @₹4500 or 1.25" ₹200@₹6000 Labor ₹12000 food ₹1500 Cement 7*450@₹3150 Door 40kg*₹130 5200 Others 5000 transport
Total ₹35000
1.5"*3/4" Pipe
Ignored
Kalai sheet 8*3 500 2.5mm 10*3 630